Physical
Plant workers fix carbon monoxide problem in The Main
By Alisha
Brown
Staff Reporter
A carbon monoxide
scare in The Main caused the eatery to be evacuated for 45 minutes
Tuesday and the Physical Plant to install carbon monoxide detectors
in the kitchen, said Richard Oliver, assistant director of facilities.
Fred Dement,
director of catering, said due to the strong winds from the storm
Monday night, the fumes from the natural gas-burning stoves, which
are normally sucked out of the building through overhead fans, were
pushed back inside.
Work
orders logged Feb. 20:
- The
Physical Plant: 59
- Residential
and Food
Services: 42
Work
orders logged Feb. 22:
- The
Physical Plant: 71
Residential and Food
- Services:
41
Total
for the week of Feb. 18-24: 335
|
The kitchen
workers noticed the natural gas odors at about 6:45 a.m., after
which the building was evacuated and the fire department called.
Dement said that the fumes had dispersed 45 minutes later, and The
Main was reopened.
The fire
department took measurements (of carbon monoxide), and at the highest
level they found, you can work up to eight hours in, Oliver
said. We have maintenance installing two carbon monoxide detectors
which are not required just to be on the safe side.
David Mestemaker,
assistant director for resources for the Physical Plant, said the
Physical Plant and Residential Services handle about 60 of these
kind of functional problems a day.
Mestemaker
said that last week, 335 work orders were logged for the entire
campus. In one day, 71 complaints were logged.
Walter Redding,
control specialist for the Physical Plant, said the Physical Plant
has 126 active personnel positions, including administrators. Within
the plant, there are six electricians, nine air conditioning and
heating specialists, five plumbers, nine finishing workers and 12
general maintenance personnel.
Oliver said
the amount of time it takes for repairs to be made depends on the
severity of the problem and the staff available.
He said for
most residence hall and cafeteria problems, repairs are usually
made within 24 hours.
We really
take pride in our maintenance, Oliver said. We may not
be the Hilton, but we want to get as close to it as possible.
Redding said
the Physical Plant handles all building and other university work
orders in three stages.
Mestemaker
said, emergency problems are handled immediately.
Oliver said
if the problem with the carbon monoxide fumes had been a fan failure,
it would have been considered an emergency work order for the Physical
Plant, but no repairs were needed.
Redding said
an example of an urgent work order would be a toilet overflowing
or a clogged sink.
Mestemaker
said routine maintenance such as desk drawer repair or the relocation
of a plug is scheduled for the first available time period within
30 days.
If its
a window blind, it may take three to four weeks if we dont
have the parts, Redding said. If its an electrical
outlet system, and we have the parts, it may be fixed overnight.
Larry Garrison,
director of facility services, said old and new buildings may not
use the same parts, but the Physical Plant is standardizing the
parts as renovations of buildings continue.
Different
companies make the same thing, so were trying to limit the
parts we use to a certain number so we can keep them in stock and
increase response time, Garrison said.
Oliver said
a weekly review of work orders is done to see which projects have
not been completed and why. He said that in recent weeks, only one
complaint was made about a work order not being completed soon enough.
If a
work order is not completed, it is probably because it has not gone
through the right channels, Oliver said.
Alisha
Brown
a.k.brown2@student.is.tcu.edu
|